Duplicate or Near-Duplicate Projects
Very similar descriptions within ~100m or identical coordinates across contracts/years.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contracts 23OD0222 and 22OD0110 have near-identical descriptions about 24 m apart (funding years 2022, 2023; ₱19.13M, ₱9.55M). Worth checking whether they cover the same works. The second contract may simply be a continuation or next phase of the same project, but the earlier one was not labeled as such.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Drainage System and Sidewalk along Karuhatan Service Road NLEX, Barangay Karuhatan, Valenzuela City22OD0110 | 100% | October 5, 2022 | October 4, 2022 | — | completedsumbong source |
Start: February 8, 2022 · Source fetched October 21, 2026
Rule Definition
Title similarity + distance or shared coordinates within municipality.
Triggering Data & citations
Similar project description near another contract in the same municipality
{
"contractId": "22OD0110",
"fundingYear": 2022,
"municipality": "CITY OF VALENZUELA (METROPOLITAN MANILA)",
"distanceMeters": 24.141128156481702,
"titleSimilarity": 0.9547135955831607
}Source documents
Possible Innocent Explanations
- Phased construction seasons
- Upstream/downstream segments recorded separately