Contractor Concentration (Flood Control)

A contractor holds a very large share of flood-control contract value in a district or province.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: GENESIS88 CONST INC received 31.2% (₱2.07B of ₱6.63B) of recorded flood-control contract value in Davao City District Engineering Office across 64 contracts and 12 contractors, at or above the 25% share threshold (HHI 0.116). This may be due to the contractor's strong track record or specialization in flood-control projects in the area.

Public record entityGENESIS88 CONST INCOrganization record →
LocationDavao City District Engineering Office
Amount₱2,070,271,100.0031.2% of peer-group contract value in public records sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Flagged peer group: Davao City District Engineering Office

Reported complete (DPWH): 28Ongoing: 0Delayed: 0Status unknown: 0
Show 22 more projects in this bucket
Construction of Revetment along R. Magsaysay Ave. Outfall, Davao City (Sta. 0+000 - Sta. 0+100)21LB0015Flood control100%September 7, 2022September 7, 2022—completedsumbong source
Construction of Seawall at Bucana, Sta. 0+000 - Sta. 0+400, Brgy. Lasang, Davao City22LB0123Flood control100%September 4, 2022September 4, 2022—completedsumbong source
Rehabilitation of Matina Pangi Creek Protecting Davao City Diversion Road (Matina Pangi Section, Left Bank) going to Matina River Outfall, Davao City22LB0287Flood control100%July 12, 2023April 15, 2023—completedsumbong source
Rehabilitation of Matina Pangi Creek Protecting Davao City Diversion Road (Matina Pangi Section, Right Bank) going to Matina River Outfall, Davao City22LB0288Flood control100%July 16, 2023April 15, 2023—completedsumbong source
Rehabilitation of Matina Pangi Creek Protecting Davao City Diversion Road (Saavedra Relocation Section, Left Bank) going to Matina River Outfall, Davao City22LB0289Flood control100%July 15, 2023April 15, 2023—completedsumbong source
Rehabilitation of Matina Pangi Creek Protecting Davao City Diversion Road (Saavedra Relocation Section, Right Bank) going to Matina River Outfall, Davao City22LB0290Flood control100%July 15, 2023April 15, 2023—completedsumbong source
Construction of Revetment along Bunawan River, Sta. 0 + 000 - Sta. 0 + 426, East Side, Davao City23LB0037100%October 27, 2023October 27, 2023—completedsumbong source
Construction of Revetment along Matina River, Asico Bridge Upstream Section, Left Bank, Davao City22LB0285100%February 24, 2023February 24, 2023—completedsumbong source
Construction of Revetment along Matina River, Asico Bridge Upstream Section, Right Bank, Davao City23LB0011100%December 29, 2023December 29, 2023—completedsumbong source
Construction of Revetment along Matina River, Matina Pangi Road Section, Right Bank, Davao City23LB0012100%November 29, 2023November 25, 2023—completedsumbong source
Construction of Revetment along Matina River, Sta. 6+207 - Sta. 6+440, Matina Pangi Br. 1 Upstream, Matina Pangi Section, Left Bank, Davao City22LB0030100%February 28, 2023February 28, 2023—completedsumbong source
Construction of Revetment along Panacan River, Sta. 1+400 - Sta. 1+700, South Side, Right Bank, Davao City22LB0122100%February 26, 2023February 26, 2023—completedsumbong source
Construction of Revetment along R. Magsaysay Ave. Outfall, Sta. 0+100 - Sta. 0+200, Davao City22LB0031100%September 24, 2022September 24, 2022—completedsumbong source
Construction of Revetment along Talomo - Puan Bypass Bridge Upstream, Left Bank, Davao City22LB0354100%August 25, 2023April 15, 2023—completedsumbong source
Construction of Revetment along Talomo - Puan Bypass Bridge Upstream, Right Bank, Davao City22LB0355100%August 3, 2023February 10, 2023—completedsumbong source
Construction of Revetment along Talomo River, Davao City21LB0246100%October 1, 2022October 1, 2022—completedsumbong source
Construction of Revetment along Talomo River, Left Bank, Davao City23LB0074100%February 15, 2024December 16, 2023—completedsumbong source
Construction of Revetment along Talomo River, Puan Bypass Road Bridge Downstream Section, Left Bank, Davao City23LB0013100%March 28, 2024March 14, 2024—completedsumbong source
Construction of Revetment along Talomo River, Sta. 3 + 542 to Sta. 3 + 817, Right Bank, Davao City21LB0296100%February 25, 2023February 25, 2023—completedsumbong source
Construction of Revetment along Talomo River, Sta. 3+542 to Sta. 3+747, Left Bank, Davao City21LB0251100%December 18, 2022December 18, 2022—completedsumbong source
Construction of Revetment along Talomo River, Sta. 3+747 to Sta. 3+952, Left Bank, Davao City21LB0252100%December 18, 2022December 18, 2022—completedsumbong source
Construction of Revetment along Talomo River, Sta. 3+817 to Sta. 4+022, Right Bank, Davao City21LB0253100%October 17, 2022October 17, 2022—completedsumbong source

Rule Definition

Share of contract value by contractor within DEO or province; flags top share > 40% or elevated HHI.

Triggering Data & citations

Contractor holds a large share of flood-control contract value in its district/province

{
  "hhi": 0.11616325152176839,
  "scope": "deo",
  "bucketKey": "deo:Davao City District Engineering Office",
  "contractor": "GENESIS88 CONST INC",
  "thresholds": {
    "share": 0.25,
    "minContracts": 3,
    "minBucketContracts": 10
  },
  "bucketTotalPhp": 6629729230.09,
  "contractorShare": 0.312270837639005,
  "contractorTotalPhp": 2070271100,
  "contractorContracts": 28
}

Possible Innocent Explanations

  • This may be due to the contractor's strong track record or specialization in flood-control projects in the area.