Contract Splitting Pattern
Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.
This is a statistical anomaly or indicator worth examining β not proof of wrongdoing, fraud, or corruption against any person.
Indicator: 5 contracts awarded to YZK BUILDERS by the same office started within 34 days, each between β±42.5M and β±50M (just under the β±50M threshold), with 4 in the same municipality. It is possible that these are separate flood control projects needed in different barangays along the same river.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error Β· Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list β not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Pinacanauan River Flood Control Project, barangay Dicamay, San Mariano, Isabela23BG0001Flood control | 100% | October 17, 2023 | September 15, 2023 | β | completedsumbong source |
Start: March 15, 2023 Β· Source fetched October 21, 2026
Rule Definition
β₯3 contracts within 120 days, each 85β100% of β±50M threshold, similar titles.
Triggering Data & citations
Cluster of contracts just under procurement threshold with similar scope
{
"deo": "Isabela 3rd District Engineering Office",
"contractId": "23BG0001",
"contractor": "YZK BUILDERS",
"windowDays": 120,
"clusterSize": 5,
"thresholdPhp": 50000000,
"contractCostPhp": 48668725.8,
"averageTitleSimilarity": 0.9454104785009713
}Source documents
Possible Innocent Explanations
- Legitimate multi-lot procurement
- Different sites under same program