Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 25OH0006 (₱137.22M) is recorded as completed in 64 days against 209 planned; similar-cost projects take a median of 377 days, putting it in the fastest 0.4%. The contractor may have deployed unusually large resources or worked in parallel to finish ahead of schedule.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Booster Pumping Station Along Estero de Tripa de Gallina Along Pedro Gil Street Barangay 869, Manila City, Phase II25OH0006Flood control | 100% | September 28, 2025 | May 6, 2025 | — | completedsumbong source |
Start: March 3, 2025 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2025-03-03T00:00:00.000Z",
"contractId": "25OH0006",
"actualEndDate": "2025-05-06T00:00:00.000Z",
"targetEndDate": "2025-09-27T00:00:00.000Z",
"contractCostPhp": 137222334.8
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo