Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 25OH0006 (₱137.22M) is recorded as completed in 64 days against 209 planned; similar-cost projects take a median of 377 days, putting it in the fastest 0.4%. The contractor may have deployed unusually large resources or worked in parallel to finish ahead of schedule.

Public record entityConstruction of Booster Pumping Station Along Estero de Tripa de Gallina Along Pedro Gil Street Barangay 869, Manila City, Phase II
LocationCITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital RegionContract 25OH0006
Amount₱137,222,334.80 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Booster Pumping Station Along Estero de Tripa de Gallina Along Pedro Gil Street Barangay 869, Manila City, Phase II25OH0006Flood control100%September 28, 2025May 6, 2025—completedsumbong source

Start: March 3, 2025 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2025-03-03T00:00:00.000Z",
  "contractId": "25OH0006",
  "actualEndDate": "2025-05-06T00:00:00.000Z",
  "targetEndDate": "2025-09-27T00:00:00.000Z",
  "contractCostPhp": 137222334.8
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo