Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 22GJ0063 lists a cost of ₱41.65M, 1.55% above its Approved Budget for the Contract of ₱41.01M. Under RA 9184, awards normally may not exceed the ABC. This may be due to a data entry error or a subsequent approved contract variation.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Rehabilitation of Iloilo Flood Control Project, Section 2, Jaro, Iloilo City, Iloilo22GJ0063Flood control | 100% | August 13, 2023 | August 13, 2023 | — | completedsumbong source |
Start: August 15, 2022 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Iloilo City District Engineering Office",
"ratio": 1.0155440414507773,
"abcPhp": 41012500,
"threshold": 0.995,
"contractId": "22GJ0063",
"contractor": "IBC INTERNATIONAL BUILDERS CORP",
"contractCostPhp": 41650000
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
- This may be due to a data entry error or a subsequent approved contract variation.