Pattern Consistent with Contract Splitting
Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: 4 contracts awarded to ROTAFLEX CONST AND DEVELOPMENT CORP FORMERLY:ROTA FLEX CONST by the same office started within 9 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 4 in the same municipality. It is possible these are separate phases or segments of a larger flood control program, each requiring its own contract.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Dampalit Riverwall (Phase 7), Barangay Dampalit, Malabon City24OA0032 | 100% | November 7, 2024 | October 21, 2024 | — | completedsumbong source |
Start: February 12, 2024 · Source fetched October 21, 2026
Rule Definition
≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.
Triggering Data & citations
Cluster of contracts just under procurement threshold with similar scope
{
"deo": "Malabon-Navotas District Engineering Office",
"contractId": "24OA0032",
"contractor": "ROTAFLEX CONST AND DEVELOPMENT CORP FORMERLY:ROTA FLEX CONST",
"windowDays": 120,
"clusterSize": 4,
"thresholdPhp": 50000000,
"contractCostPhp": 48999924.88,
"averageTitleSimilarity": 0.8750888580534641
}Source documents
Possible Innocent Explanations
- Legitimate multi-lot procurement
- Different sites under same program