Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24CC0022 (₱77.20M) is recorded as completed in 40 days against 239 planned; similar-cost projects take a median of 285 days, putting it in the fastest 0.3%. This could be due to unusually efficient work, pre-fabrication, or early reporting of completion.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Riverbank Protection Structure at Barangay Sapang Bayan, Calumpit, Bulacan24CC0022 | 100% | October 3, 2024 | March 18, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: February 7, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-02-07T00:00:00.000Z",
"contractId": "24CC0022",
"actualEndDate": "2024-03-18T00:00:00.000Z",
"targetEndDate": "2024-10-02T00:00:00.000Z",
"contractCostPhp": 77199865.91
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo
- This could be due to unusually efficient work, pre-fabrication, or early reporting of completion.
