Love the Philippines

Anomaly / indicator worth examining — not an accusation.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Bid-Ceiling Hugging

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 22PA0099 lists a cost of ₱49.50M, 1.02% above its Approved Budget for the Contract of ₱49.00M. Under RA 9184, awards normally may not exceed the ABC. This may be due to a data entry error or a post-bid adjustment not reflected in the ABC.

Public record entityConstruction of Mudeng Flood Control Structure (Phase 3), Barangay Mudeng, La Paz, Abra
LocationLA PAZ (ABRA), ABRA, Cordillera Administrative RegionContract 22PA0099
Amount₱49,497,500.00101.02% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Mudeng Flood Control Structure (Phase 3), Barangay Mudeng, La Paz, Abra22PA0099Flood control100%December 5, 2022December 5, 2022—completedsumbong source

Start: May 24, 2022 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Abra District Engineering Office",
  "ratio": 1.0101550007220912,
  "abcPhp": 48999905.92,
  "threshold": 0.995,
  "contractId": "22PA0099",
  "contractor": "739 BUILDERS",
  "contractCostPhp": 49497500
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate