Bid-Ceiling Hugging
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23CI0129 lists a cost of ₱19.80M, 0.10% above its Approved Budget for the Contract of ₱19.78M. Under RA 9184, awards normally may not exceed the ABC. This may be due to a rounding or data entry error.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Reinforced Concrete Slope Protection along Sapang Balen River, Sitio Mapiña, Magalang, Pampanga23CI0129 | 100% | October 20, 2023 | October 20, 2023 | — | completedsumbong source |
Start: May 24, 2023 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Pampanga 3rd District Engineering Office",
"ratio": 1.0010112342583304,
"abcPhp": 19777019.85,
"threshold": 0.995,
"contractId": "23CI0129",
"contractor": "M C J VALENZUELA CONST ENT",
"contractCostPhp": 19797019.05
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate