Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 22LB0373 was awarded at 100.00% of its ABC. Across its 29 recorded contracts, GENESIS88 CONST INC was awarded at ≥99.5% of ABC 29 times (100.0%), versus 70.4% for flood-control contracts overall. This may be due to highly competitive bidding or precise cost estimation.

Public record entityConstruction of Flood Mitigation Structure at Purok 16, Block 2, Barangay Catalunan Pequeño, Davao City
LocationDAVAO CITY (DAVAO DEL SUR), DAVAO DEL SUR, Region XIContract 22LB0373
Amount₱6,860,000.00100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Mitigation Structure at Purok 16, Block 2, Barangay Catalunan Pequeño, Davao City22LB0373Flood control100%July 27, 2023July 27, 2023—completedsumbong source

Start: April 13, 2022 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Davao City District Engineering Office",
  "ratio": 1,
  "abcPhp": 6860000,
  "threshold": 0.995,
  "contractId": "22LB0373",
  "contractor": "GENESIS88 CONST INC",
  "contractCostPhp": 6860000
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate
  • This may be due to highly competitive bidding or precise cost estimation.