Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23FN0056 was awarded at 100.00% of its ABC. Across its 67 recorded contracts, SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP was awarded at ≥99.5% of ABC 61 times (91.0%), versus 70.4% for flood-control contracts overall. This may be due to precise cost estimation or competitive bidding that matched the ABC exactly.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Bank Protection Structure along Pawili River, Salvacion Section, Bula, Camarines Sur23FN0056Flood control | 100% | April 9, 2024 | April 9, 2024 | — | completedsumbong source |
Start: June 20, 2023 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Camarines Sur 5th District Engineering Office",
"ratio": 1,
"abcPhp": 96500000,
"threshold": 0.995,
"contractId": "23FN0056",
"contractor": "SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP",
"contractCostPhp": 96500000
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
- This may be due to precise cost estimation or competitive bidding that matched the ABC exactly.
