Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23HO0225 was awarded at 100.00% of its ABC. Across its 88 recorded contracts, QM BUILDERS was awarded at ≥99.5% of ABC 84 times (95.5%), versus 70.4% for flood-control contracts overall. It is possible that the contract price matched the ABC due to precise cost estimation or competitive bidding that reached the maximum allowed amount.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Drainage System along Brgy. Tunga, Moalboal, Cebu23HO0225 | 100% | March 16, 2024 | March 16, 2024 | — | completedsumbong source |
Start: June 27, 2023 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Cebu 7th District Engineering Office",
"ratio": 0.9999887226127074,
"abcPhp": 26458256,
"threshold": 0.995,
"contractId": "23HO0225",
"contractor": "QM BUILDERS",
"contractCostPhp": 26457957.62
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate