Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Pattern Consistent with Contract Splitting

Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: 5 contracts awarded to ANORE CONST by the same office started within 0 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 5 in the same municipality. It is possible that these are separate flood control projects for different sections of the river, planned together for efficiency.

Public record entityConstruction of Flood Control Structure, Amnay River, Sta. 1+303 - Sta. 1+680, Guitong Section, Sablayan, Occidental Mindoro
LocationSABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-BContract 22E00071
Amount₱43,424,984.72 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Structure, Amnay River, Sta. 1+303 - Sta. 1+680, Guitong Section, Sablayan, Occidental Mindoro22E00071Flood control100%July 3, 2023July 3, 2023—completedsumbong source

Start: July 6, 2022 · Source fetched October 21, 2026

Rule Definition

≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.

Triggering Data & citations

Cluster of contracts just under procurement threshold with similar scope

{
  "deo": "Mindoro Occidental District Engineering Office",
  "contractId": "22E00071",
  "contractor": "ANORE CONST",
  "windowDays": 120,
  "clusterSize": 5,
  "thresholdPhp": 50000000,
  "contractCostPhp": 43424984.72,
  "averageTitleSimilarity": 0.9092078727018496
}

Possible Innocent Explanations

  • Legitimate multi-lot procurement
  • Different sites under same program