Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24BG0068 (₱96.49M) is recorded as completed in 42 days against 327 planned; similar-cost projects take a median of 285 days, putting it in the fastest 0.4%. This could be due to early completion reporting, pre-existing work, or efficient project management.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of River Flood Control Project along Ganano River Bank, Barangay San Antonio Upstream (Sta. 0+465.50 - Sta. 0+928.20), Alicia, Isabela24BG0068 | 100% | May 17, 2025 | August 5, 2024 | — | completedsumbong source |
Start: June 24, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-06-24T00:00:00.000Z",
"contractId": "24BG0068",
"actualEndDate": "2024-08-05T00:00:00.000Z",
"targetEndDate": "2025-05-16T00:00:00.000Z",
"contractCostPhp": 96489406.74
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo
- This could be due to early completion reporting, pre-existing work, or efficient project management.