Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23CI0039 (₱29.21M) is recorded as completed in 63 days against 119 planned; similar-cost projects take a median of 239 days, putting it in the fastest 1.6%. The contractor may have used more resources or efficient methods, or the planned duration may have been overestimated.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Reinforced Concrete Slope Protection with Steel Sheet Piles Foundation along Abacan River, Brgy. Amsic to Brgy. Anunas, Angeles City, Pampanga Phase 123CI0039 | 100% | July 17, 2023 | May 22, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: March 20, 2023 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2023-03-20T00:00:00.000Z",
"contractId": "23CI0039",
"actualEndDate": "2023-05-22T00:00:00.000Z",
"targetEndDate": "2023-07-16T00:00:00.000Z",
"contractCostPhp": 29205689.03
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo