Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 22A00289 (₱7.89M) is recorded as completed in 29 days against 29 planned; similar-cost projects take a median of 147 days, putting it in the fastest 0.6%. The project may have been unusually efficient or had a smaller scope than typical for its cost.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Slope Protection Works along San Francisco - Ambitacay Road, Agoo, La Union Sta. 000 + 650 - Sta. 000 + 71022A00289 | 100% | December 2, 2022 | December 2, 2022 | — | completedsumbong source |
Start: November 3, 2022 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2022-11-03T00:00:00.000Z",
"contractId": "22A00289",
"actualEndDate": "2022-12-02T00:00:00.000Z",
"targetEndDate": "2022-12-01T00:00:00.000Z",
"contractCostPhp": 7885653.01
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo