Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24AI0007 (₱48.95M) is recorded as completed in 41 days against 200 planned; similar-cost projects take a median of 239 days, putting it in the fastest 0.5%. The project may have been completed quickly due to efficient work, pre-existing preparations, or early completion reporting.

Public record entityConstruction of Flood Control Structure along Aloragat River, Barangay Bugayong-Vacante, Binalonan, Pangasinan (Package 4)
LocationBINALONAN (PANGASINAN), PANGASINAN, Region IContract 24AI0007
Amount₱48,950,141.11 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Structure along Aloragat River, Barangay Bugayong-Vacante, Binalonan, Pangasinan (Package 4)24AI0007100%September 1, 2024March 26, 2024—completedsumbong source

Start: February 14, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-02-14T00:00:00.000Z",
  "contractId": "24AI0007",
  "actualEndDate": "2024-03-26T00:00:00.000Z",
  "targetEndDate": "2024-08-31T00:00:00.000Z",
  "contractCostPhp": 48950141.11
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo