Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24A00310 (₱48.25M) is recorded as completed in 73 days against 183 planned; similar-cost projects take a median of 239 days, putting it in the fastest 2.2%. The contractor may have deployed extra resources or worked overtime to finish ahead of schedule.

Public record entityConstruction of Flood Control Mitigation Structure along Agno River and Allied Rivers, Rosales, Pangasinan (Package 2)
LocationROSALES (PANGASINAN), PANGASINAN, Region IContract 24A00310
Amount₱48,248,674.94 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Mitigation Structure along Agno River and Allied Rivers, Rosales, Pangasinan (Package 2)24A00310100%November 2, 2024July 15, 2024—completedsumbong source

Start: May 3, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-05-03T00:00:00.000Z",
  "contractId": "24A00310",
  "actualEndDate": "2024-07-15T00:00:00.000Z",
  "targetEndDate": "2024-11-01T00:00:00.000Z",
  "contractCostPhp": 48248674.94
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo