Love the Philippines

Anomaly / indicator worth examining — not an accusation.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Bid-Ceiling Hugging

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 22HO0039 was awarded at 100.00% of its ABC. Across its 88 recorded contracts, QM BUILDERS was awarded at ≥99.5% of ABC 84 times (95.5%), versus 70.4% for flood-control contracts overall. It is possible that the winning bid matched the ABC due to precise cost estimation or lack of competition.

Public record entityConstruction of Alegria Seawall, Alegria, Cebu
LocationALEGRIA (CEBU), CEBU, Region VIIContract 22HO0039
Amount₱86,844,519.15100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Alegria Seawall, Alegria, Cebu22HO0039Flood control100%October 3, 2022October 3, 2022—completedsumbong source

Start: February 21, 2022 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Cebu 7th District Engineering Office",
  "ratio": 1,
  "abcPhp": 86844519.15,
  "threshold": 0.995,
  "contractId": "22HO0039",
  "contractor": "QM BUILDERS",
  "contractCostPhp": 86844519.15
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate