Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 22, 2026

High Concurrent Workload for One Contractor

Contractor linked to many simultaneous projects or very high total value vs peers.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: EGB CONST CORP FORMERLY: EGB CONST holds 37 flood-control contracts worth ₱3.02B, 2.98× the 95th-percentile contractor total (₱1.01B); up to 16 ran at the same time. This is a capacity question worth examining. The contractor may be a large, specialized firm or won many bids in a region with high flood-control needs.

Public record entityEGB CONST CORP FORMERLY: EGB CONSTOrganization record →
Location—
AmountData not yet available sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 37Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Alicaocao Flood Control Project, Cauayan City, Isabela23BH0088Flood control100%August 14, 2023August 12, 2023—completedsumbong source
Construction of Bakir Flood Control Structure along Lamut River, Barangay Bakir, Bagabag, Nueva Vizcaya24BI0041Flood control100%February 16, 2025July 22, 2024—completedsumbong source
Construction of Barangay Fugu Sur to Fugu Norte Flood Control System, Phase II, Tumauini, Isabela22BE0023Flood control100%October 3, 2022September 9, 2022—completedsumbong source
Construction of Canayun-Sirit-Dana-Ili Flood Control along Abulug River (Sta. 13+300 - Sta. 13+580) left side, Abulug, Cagayan22BC0024Flood control100%June 9, 2023June 9, 2023—completedsumbong source
Construction of Canayun-Sirit-Dana-ili Flood Control along abulug river, abulug, Cagayan22BC0121Flood control100%November 5, 2022September 30, 2022—completedsumbong source
Construction of Dipangit Flood Control Structure, Section 1, Jones, Isabela24BH0196Flood control100%March 21, 2025December 7, 2024—completedsumbong source
Show 31 more projects in this bucket
Construction of Dipangit Flood Control Structure, Section 2, Jones, Isabela24BH0195Flood control100%March 17, 2025December 7, 2024—completedsumbong source
Construction of Dipangit Flood Control Structure, Section 3, Jones, Isabela24BH0187Flood control100%April 10, 2025August 22, 2024—completedsumbong source
Construction of Dipangit Flood Control Structure, Section 4, Jones, Isabela24BH0211Flood control100%April 16, 2025November 11, 2024—completedsumbong source
Construction of Flood Control and Drainage Structures (FCDS- Package 2) along Magat River, Magapuy Section, Bayombong, Nueva Viscaya24BI0007Flood control100%January 25, 2025May 21, 2024—completedsumbong source
Construction of Flood Control and Drainage Structures (FCDS- Package 3) along Magat River, Baretbet Section, Bagabag, Nueva Viscaya24BI0009Flood control100%April 11, 2025April 11, 2025—completedsumbong source
Construction of Flood Control and Drainage Structures (FCDS- Package 5) along Magat River, Bagahabag Section, Solano, Nueva Viscaya24BI0034Flood control100%January 25, 2025May 21, 2024—completedsumbong source
Construction of Flood Control and Drainage Structures (FCDS- Package 6) along Magat River, Santa Lucia Section, Bagabag, Nueva Viscaya24BI0021Flood control100%February 15, 2025May 21, 2024—completedsumbong source
Construction of Flood Control and Drainage Structures (FCDS- Package 7) along Magat River, Magapuy Section, Bayombong, Nueva Viscaya24BI0008Flood control100%January 25, 2025May 21, 2024—completedsumbong source
Construction of Flood Control and Drainage Structures (FCDS- Package 8) along Magat River, Baretbet Section, Bagabag, Nueva Viscaya24BI0015Flood control100%April 10, 2025April 10, 2025—completedsumbong source
Construction of Flood Control and Drainage Structures (FCDS) along Magat River, Kinacao Section, Bagabag, Nueva Vizcaya23BI0028Flood control100%March 9, 2024October 15, 2023—completedsumbong source
Construction of Flood Control at Casbu, Guindulman, Bohol23HB0062Flood control100%February 18, 2024February 18, 2024—completedsumbong source
Construction of Flood Control Project along Ilagan River (Sta. 0+000 - Sta. 0+190), Brgy. Aggasian, City of Ilagan, Isabela22BE0039Flood control100%February 5, 2023February 5, 2023—completedsumbong source
Construction of Flood Control Project along Ilagan River (Sta. 0+000 - Sta. 0+208), Brgy. Bangag-Manaring, City of Ilagan, Isabela22BE0046Flood control100%February 19, 2023February 19, 2023—completedsumbong source
Construction of Flood Control Project along Ilagan River (Sta. 0+000 - Sta. 0+229), Brgy. Camunatan, City of Ilagan, Isabela22BE0025Flood control100%February 5, 2023January 23, 2023—completedsumbong source
Construction of Flood Control Project along Ilagan River (Sta. 0+000 - Sta. 0+944), Brgy. Fugu, City of Ilagan, Isabela22BE0032Flood control100%November 10, 2022November 9, 2022—completedsumbong source
Construction of Flood Control Structure with Channelization of Waterway along Aggub- San Juan Creek, Cabagan, Isabela22BE0018Flood control100%August 27, 2022August 27, 2022—completedsumbong source
Construction of Flood Control Structure with Channelization of Waterway along Balasig- Magassi Creek, Cabagan, Isabela22BE0017Flood control100%August 27, 2022August 27, 2022—completedsumbong source
Construction of Flood Control Structure, Barangay II, Section 2, Jones, Isabela23BH0173Flood control100%February 8, 2024December 7, 2023—completedsumbong source
Construction of Flood Control Structure, Brgy. Balite, Gloria, Oriental Mindoro22EI0096Flood control100%December 19, 2022December 19, 2022—completedsumbong source
Construction of Flood Mitigation Structure along Cagayan River - Phase II, Barangay Alibagu, City of Ilagan, Isabela24BE0016Flood control100%February 6, 2025December 15, 2024—completedsumbong source
Construction of Flood Mitigation Structure along Cagayan River, Barangay Alibagu, City of Ilagan, Isabela23BE0035Flood control100%January 24, 2024November 24, 2023—completedsumbong source
Construction of Flood Mitigation Structure along Cagayan River, Barangay Mozzozzin Sur, Sta. Maria, Isabela23BE0108Flood control100%January 18, 2024October 23, 2023—completedsumbong source
Construction of Flood Mitigation Structure along Ilagan River, Phase II, Brgy. Camunatan, City of Ilagan, Isabela23BE0051Flood control100%April 7, 2024December 18, 2023—completedsumbong source
Construction of flood mitigation structure along magat river with channel excavation/desilting works, Barangay Turod, Municipality of Reina Mercedes, Province of Isabela21BG0154Flood control100%November 26, 2022November 26, 2022—completedsumbong source
Construction of River Control at Oway River below the Dicaruyan-Sapinit Bridge, Barangay Dicaruyan, Divilacan, Isabela22BE0055Flood control100%July 22, 2022July 22, 2022—completedsumbong source
Pinacanauan River Flood Management Projects, Camasi- Centro, Peñablanca, Cagayan22BD0090Flood control100%March 22, 2023December 9, 2022—completedsumbong source
Reconstruction of Canayun-Sirit-Dana-ili Flood Control Along Abulug River , Abulug, Cagayan Sta. 12+700 - Sta. 12+860, Sta. 13+220 - Sta. 13+300 (L/S)21BC0070Flood control100%December 12, 2022January 12, 2023—completedsumbong source
Reconstruction of Canayun-Sirit-Dana-ili Flood Control Along Abulug River , Abulug,Cagayan Sta. 12+860 - Sta.12+980(L/S)21BC0061Flood control100%September 9, 2022September 9, 2022—completedsumbong source
Construction of Balug Flood Control at Tumauini, Isabela23B00009100%August 25, 2024August 23, 2024—completedsumbong source
Construction of Slope Protection Works for Cagayan River Basin, Cagayan River at Sta. Maria, Isabela23B00057100%May 16, 2024February 29, 2024—completedsumbong source
Improvement of Slope Protection Structures along Abacan Creek (Downstream), Pampanga22CI0037100%October 19, 2022October 19, 2022—completedsumbong source

Rule Definition

Active project count and total value vs peer 95th percentile.

Triggering Data & citations

Contractor carries far more concurrent flood-control value than peers

{
  "contractor": "EGB CONST CORP FORMERLY: EGB CONST",
  "projectCount": 37,
  "totalValuePhp": 3020411074.1800003,
  "peerP95TotalPhp": 1014143494.4100002,
  "activeProjectCount": 0,
  "simultaneousThreshold": 25
}

Possible Innocent Explanations

  • Large national firm with many concurrent government clients
  • Data groups joint ventures under one name