Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 25CF0039 (₱96.01M) is recorded as completed in 63 days against 350 planned; similar-cost projects take a median of 285 days, putting it in the fastest 1.2%. The project may have been completed unusually quickly due to favorable conditions, early preparation, or overestimated planning duration.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Rehabilitation of River Bank Structure along Pampanga River, Barangay San Pablo, Jaen, Nueva Ecija25CF0039Flood control | 100% | February 5, 2026 | April 24, 2025 | — | completedsumbong source |
Start: February 20, 2025 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2025-02-20T00:00:00.000Z",
"contractId": "25CF0039",
"actualEndDate": "2025-04-24T00:00:00.000Z",
"targetEndDate": "2026-02-04T00:00:00.000Z",
"contractCostPhp": 96013671.84
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo