Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23BH0173 was awarded at 100.00% of its ABC. Across its 37 recorded contracts, EGB CONST CORP FORMERLY: EGB CONST was awarded at ≥99.5% of ABC 36 times (97.3%), versus 70.4% for flood-control contracts overall. This may be due to highly competitive bidding where the winning bid matches the ABC exactly.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure, Barangay II, Section 2, Jones, Isabela23BH0173Flood control | 100% | February 8, 2024 | December 7, 2023 | — | completedsumbong source |
Start: April 17, 2023 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Isabela 4th District Engineering Office",
"ratio": 0.9999989664248705,
"abcPhp": 96500000,
"threshold": 0.995,
"contractId": "23BH0173",
"contractor": "EGB CONST CORP FORMERLY: EGB CONST",
"contractCostPhp": 96499900.26
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
- This may be due to highly competitive bidding where the winning bid matches the ABC exactly.