Pattern Consistent with Contract Splitting
Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: 3 contracts awarded to GOLDRICH CONST & TRADING by the same office started within 58 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 3 in the same municipality. These may be separate projects for different sections of flood mitigation in the same city, planned and bid out at the same time.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Mitigation Facility/Drainage System along Bued River (Tributaries) Sta. 0+190 - Sta. 0+640, Baguio City22PD0018 | 100% | February 25, 2023 | January 20, 2023 | — | completedsumbong source |
Start: April 10, 2022 · Source fetched October 21, 2026
Rule Definition
≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.
Triggering Data & citations
Cluster of contracts just under procurement threshold with similar scope
{
"deo": "Baguio City District Engineering Office",
"contractId": "22PD0018",
"contractor": "GOLDRICH CONST & TRADING",
"windowDays": 120,
"clusterSize": 3,
"thresholdPhp": 50000000,
"contractCostPhp": 49000000,
"averageTitleSimilarity": 0.9038378179728832
}Source documents
Possible Innocent Explanations
- Legitimate multi-lot procurement
- Different sites under same program
