Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24BF0013 (₱96.49M) is recorded as completed in 43 days against 370 planned; similar-cost projects take a median of 285 days, putting it in the fastest 0.4%. The project may have been completed quickly due to favorable weather, efficient management, or prior preparatory work.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Slope Protection Works for Cagayan River Basin, Siffu River, San Placido, Roxas, Isabela24BF0013 | 100% | March 9, 2025 | April 16, 2024 | — | completedsumbong source |
Start: March 4, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-03-04T00:00:00.000Z",
"contractId": "24BF0013",
"actualEndDate": "2024-04-16T00:00:00.000Z",
"targetEndDate": "2025-03-08T00:00:00.000Z",
"contractCostPhp": 96488772.99
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo
