Duplicate or Near-Duplicate Projects
Very similar descriptions within ~100m or identical coordinates across contracts/years.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contracts 23CC0121 and 24CC0358 have near-identical descriptions about 22 m apart (funding years 2023, 2024; ₱28.95M, ₱26.53M). Worth checking whether they cover the same works. It is possible that the second project is a continuation or extension of the first, or covers a nearby but distinct section not specified in the title.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Revetment at Barangay San Jose, Paombong, Bulacan24CC0358 | 100% | September 14, 2024 | August 16, 2024 | — | completedsumbong source |
Start: April 18, 2024 · Source fetched October 21, 2026
Rule Definition
Title similarity + distance or shared coordinates within municipality.
Triggering Data & citations
Similar project description near another contract in the same municipality
{
"contractId": "24CC0358",
"fundingYear": 2024,
"municipality": "PAOMBONG (BULACAN)",
"distanceMeters": 22.309201682846425,
"titleSimilarity": 0.9294505494505494
}Source documents
Possible Innocent Explanations
- Phased construction seasons
- Upstream/downstream segments recorded separately