Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 22LB0355 was awarded at 100.00% of its ABC. Across its 29 recorded contracts, GENESIS88 CONST INC was awarded at ≥99.5% of ABC 29 times (100.0%), versus 70.4% for flood-control contracts overall. This may be due to highly competitive bidding or precise cost estimation.

Public record entityConstruction of Revetment along Talomo - Puan Bypass Bridge Upstream, Right Bank, Davao City
LocationDAVAO CITY (DAVAO DEL SUR), DAVAO DEL SUR, Region XIContract 22LB0355
Amount₱96,500,000.00100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Revetment along Talomo - Puan Bypass Bridge Upstream, Right Bank, Davao City22LB0355100%August 3, 2023February 10, 2023—completedsumbong source

Start: June 21, 2022 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Davao City District Engineering Office",
  "ratio": 1,
  "abcPhp": 96500000,
  "threshold": 0.995,
  "contractId": "22LB0355",
  "contractor": "GENESIS88 CONST INC",
  "contractCostPhp": 96500000
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate
  • This may be due to highly competitive bidding or precise cost estimation.