Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 22CL0073 lists a cost of ₱39.30M, 1.03% above its Approved Budget for the Contract of ₱38.90M. Under RA 9184, awards normally may not exceed the ABC. This may be due to a data entry error or a late adjustment to the ABC that was not reflected in the records.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Mitigation Structure,Tambak River (Upstream) Phase II, Iba, Zambales22CL0073Flood control | 100% | September 30, 2022 | September 28, 2022 | — | completedsumbong source |
Start: April 4, 2022 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Zambales 1st District Engineering Office",
"ratio": 1.01026289583236,
"abcPhp": 38903735.02,
"threshold": 0.995,
"contractId": "22CL0073",
"contractor": "CDC CONST & SUPPLIES",
"contractCostPhp": 39303000
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
- This may be due to a data entry error or a late adjustment to the ABC that was not reflected in the records.