Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 25MG0034 (₱14.69M) is recorded as completed in 56 days against 122 planned; similar-cost projects take a median of 182 days, putting it in the fastest 2.1%. The contractor may have deployed extra resources or worked overtime to finish ahead of schedule.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Ala RIS Protection Works, Sto. Niño, South Cotabato25MG0034Flood control | 100% | June 30, 2025 | April 25, 2025 | — | completedsumbong source |
Start: February 28, 2025 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2025-02-28T00:00:00.000Z",
"contractId": "25MG0034",
"actualEndDate": "2025-04-25T00:00:00.000Z",
"targetEndDate": "2025-06-29T00:00:00.000Z",
"contractCostPhp": 14689979.39
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo