Pattern Consistent with Contract Splitting
Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: 5 contracts awarded to NFH CONST & SUPPLY by the same office started within 16 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 3 in the same municipality. It is common for flood control projects to be distributed across multiple barangays and rivers within a district, resulting in several similar-sized contracts awarded around the same time.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Dike (along San Isidro-Aslong-Palangon Creek) within Bicol River Basin, Brgy. Aslong, Libmanan, Camarines Sur22FE0044 | 100% | October 6, 2022 | October 6, 2022 | — | completedsumbong source |
Start: March 16, 2022 · Source fetched October 21, 2026
Rule Definition
≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.
Triggering Data & citations
Cluster of contracts just under procurement threshold with similar scope
{
"deo": "Camarines Sur 2nd District Engineering Office",
"contractId": "22FE0044",
"contractor": "NFH CONST & SUPPLY",
"windowDays": 120,
"clusterSize": 5,
"thresholdPhp": 50000000,
"contractCostPhp": 48015893,
"averageTitleSimilarity": 0.8790617942580291
}Source documents
Possible Innocent Explanations
- Legitimate multi-lot procurement
- Different sites under same program