Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 23FN0008 was awarded at 100.00% of its ABC. Across its 67 recorded contracts, SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP was awarded at ≥99.5% of ABC 61 times (91.0%), versus 70.4% for flood-control contracts overall. This may be due to precise cost estimation or rounding to match the ABC exactly.

Public record entityConstruction of Flood Control along Cagas Bridge (Downstream Section), Nabua, Camarines Sur
LocationNABUA (CAMARINES SUR), CAMARINES SUR, Region VContract 23FN0008
Amount₱96,402,424.49100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control along Cagas Bridge (Downstream Section), Nabua, Camarines Sur23FN0008Flood control100%December 28, 2023December 22, 2023—completedsumbong source

Start: February 17, 2023 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Camarines Sur 5th District Engineering Office",
  "ratio": 0.9999994656776242,
  "abcPhp": 96402476,
  "threshold": 0.995,
  "contractId": "23FN0008",
  "contractor": "SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP",
  "contractCostPhp": 96402424.49
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate
  • This may be due to precise cost estimation or rounding to match the ABC exactly.