Schedule / Date Anomalies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24CC0032 (₱77.19M) is recorded as completed in 72 days against 239 planned; similar-cost projects take a median of 285 days, putting it in the fastest 1.8%. The contractor may have deployed unusually large resources or worked in favorable conditions, allowing for rapid completion.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Riverbank Protection Structure at Barangay Bulihan, Malolos City, Bulacan24CC0032 | 100% | October 3, 2024 | April 19, 2024 | — | completedsumbong source |
Start: February 7, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-02-07T00:00:00.000Z",
"contractId": "24CC0032",
"actualEndDate": "2024-04-19T00:00:00.000Z",
"targetEndDate": "2024-10-02T00:00:00.000Z",
"contractCostPhp": 77188533.89
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo