Schedule / Date Anomalies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24OB0331 (₱9.55M) is recorded as completed in 29 days against 29 planned; similar-cost projects take a median of 147 days, putting it in the fastest 0.6%. The project may have been completed quickly due to favorable conditions, efficient management, or prior preparatory work.

Public record entityImprovement works along Marikina River, Second District, Marikina City
LocationCITY OF MARIKINA (METROPOLITAN MANILA), MARIKINA CITY, National Capital RegionContract 24OB0331
Amount₱9,550,193.00 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Improvement works along Marikina River, Second District, Marikina City24OB0331Flood control100%May 7, 2024May 7, 2024—completedsumbong source

Start: April 8, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-04-08T00:00:00.000Z",
  "contractId": "24OB0331",
  "actualEndDate": "2024-05-07T00:00:00.000Z",
  "targetEndDate": "2024-05-06T00:00:00.000Z",
  "contractCostPhp": 9550193
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo