Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 21LB0299 was awarded at 100.00% of its ABC. Across its 115 recorded contracts, LEGACY CONST CORP FORMERLY: LEGACY CONST was awarded at ≥99.5% of ABC 100 times (87.0%), versus 70.4% for flood-control contracts overall. This may result from competitive bidding where the lowest bid matches the ABC exactly.

Public record entityConstruction of Revetment along Matina River, Matina Pangi Downstream, Matina Pangi Section, Davao City
LocationDAVAO DEL SUR, Region XIContract 21LB0299
Amount₱87,573,750.00100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Revetment along Matina River, Matina Pangi Downstream, Matina Pangi Section, Davao City21LB0299100%May 31, 2023May 31, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: December 5, 2021 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Davao City District Engineering Office",
  "ratio": 1,
  "abcPhp": 87573750,
  "threshold": 0.995,
  "contractId": "21LB0299",
  "contractor": "LEGACY CONST CORP FORMERLY: LEGACY CONST",
  "contractCostPhp": 87573750
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate

Connected records

Where this project sits

Place (PSGC)
Region XI (Davao Region)City of DavaoMatina Crossing
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Active fault2.8 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)mediumUP NOAH Center / DOST-PAGASA (Project NOAH)Landslideoutside mapped landslide zonesUP NOAH Center / UP NIGS (Project NOAH)Storm surgenot inundated even at SSA4 (>5 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.