Pattern Consistent with Contract Splitting

Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: 14 contracts awarded to 739 BUILDERS by the same office started within 62 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 5 in the same municipality. It is possible that the projects were planned separately for different flood-prone areas and happened to be implemented in the same period.

Public record entityConstruction of Buli Flood Mitigation Facilities along Major River Basin (Phase III), Sta. 5 + 400 - Sta. 5 + 700, La Paz, Abra
LocationLA PAZ (ABRA), ABRA, Cordillera Administrative RegionContract 22PA0140
Amount₱48,997,900.00 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Buli Flood Mitigation Facilities along Major River Basin (Phase III), Sta. 5 + 400 - Sta. 5 + 700, La Paz, Abra22PA0140Flood control100%January 1, 2023November 28, 2022—completedsumbong source

Start: June 20, 2022 · Source fetched October 21, 2026

Rule Definition

≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.

Triggering Data & citations

Cluster of contracts just under procurement threshold with similar scope

{
  "deo": "Abra District Engineering Office",
  "contractId": "22PA0140",
  "contractor": "739 BUILDERS",
  "windowDays": 120,
  "clusterSize": 14,
  "thresholdPhp": 50000000,
  "contractCostPhp": 48997900,
  "averageTitleSimilarity": 0.8481382823764025
}

Possible Innocent Explanations

  • Legitimate multi-lot procurement
  • Different sites under same program