Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Pattern Consistent with Contract Splitting

Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: 3 contracts awarded to LE BRON CONST by the same office started within 29 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 3 in the same municipality. It is possible that these are separate legitimate projects in different barangays or locations within Quezon City, each requiring its own contract.

Public record entityRehabilitation of Flood Control Structure of Villa Verde Creek, Barangay Sta. Monica, Quezon City
LocationQUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital RegionContract 23OF0122
Amount₱49,499,890.92 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Rehabilitation of Flood Control Structure of Villa Verde Creek, Barangay Sta. Monica, Quezon City23OF0122Flood control100%January 29, 2024December 18, 2023—completedsumbong source

Start: April 5, 2023 · Source fetched October 21, 2026

Rule Definition

≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.

Triggering Data & citations

Cluster of contracts just under procurement threshold with similar scope

{
  "deo": "Quezon City 1st District Engineering Office",
  "contractId": "23OF0122",
  "contractor": "LE BRON CONST",
  "windowDays": 120,
  "clusterSize": 3,
  "thresholdPhp": 50000000,
  "contractCostPhp": 49499890.92,
  "averageTitleSimilarity": 0.7320151318554035
}

Possible Innocent Explanations

  • Legitimate multi-lot procurement
  • Different sites under same program