Cross-Source Mismatch (PhilGEPS vs DPWH)
Linked PhilGEPS award amount or awardee disagrees with Sumbong contract row.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: PhilGEPS award 22MG0006 lists ₱96.75M to NIRVANA CONSTRUCTION AND SUPPLIES, while DPWH records contract 22MG0006 at ₱49.00M to NIRVANA CONST & SUPPLIES / FFJJ CONST. This may be due to a contract variation, joint venture arrangement, or a data entry update after the award.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Riverbank Protection along Marbel River, Brgy. Carpenter Hill, Koronadal City, South Cotabato22MG0006Flood control | 100% | September 12, 2022 | October 7, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: February 18, 2022 · Source fetched October 21, 2026
Rule Definition
Compares linked award and project contractor/cost above tolerance.
Triggering Data & citations
Linked PhilGEPS award fields disagree with DPWH/Sumbong contract record
{
"linkId": "0b4f4144-854c-41f3-a171-2491b96556a2",
"awardId": "d5d52562-f489-4579-90df-c47629502efa",
"linkScore": 1,
"nameMismatch": false,
"amountMismatch": true,
"awardAmountPhp": 96746061.56,
"linkValidation": "philgeps_ref equals DPWH contract ID",
"projectCostPhp": 48999998.25,
"philgepsAwardee": "NIRVANA CONSTRUCTION AND SUPPLIES"
}Source documents
Possible Innocent Explanations
- This may be due to a contract variation, joint venture arrangement, or a data entry update after the award.