Flood Control and Drainage24OH0090

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST. OF DRAINAGE SYSTEM, ZONE 60,61 AND 62, BACOOD,STA.MESA, MANILA

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST. OF DRAINAGE SYSTEM, ZONE 60,61 AND 62, BACOOD,STA.MESA, MANILA is a DPWH-tracked public work in South Manila DEO, National Capital Region. Reported contract value: ₱48,923,862.84. Status: Reported complete (DPWH). Contractor on record: AMETHYST HORIZON BUILDERS AND GEN CONTRACTOR AND DEVELOPMENT CORP. Figures trace to dpwh.

South Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 77%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Binondo, Barangay 281, Manila City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-F-24-0016515

₱97,500.00 · FY2024

Released to Regional Office - XIII (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

154 projects · ₱9.6B total · 12 flags

4. Implementation

Contract Amount

₱48,923,862.84

Progress

Reported complete (DPWH)

Start Date

May 6, 2024

Target End

April 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.