PAMANA 202424IJ0102

(RE-ADVERTISED) CONSTRUCTION OF BRGY. MADUROTO BRIDGE (ALONG MATUGUINAO - LAS NAVAS ROAD) PHASE IV - BRGY. MADUROTO, MATUGUINAO, SAMAR

(RE-ADVERTISED) CONSTRUCTION OF BRGY. MADUROTO BRIDGE (ALONG MATUGUINAO - LAS NAVAS ROAD) PHASE IV - BRGY. MADUROTO, MATUGUINAO, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱97,997,342.94. Status: Past target date (DPWH On-Going). Contractor on record: NORTHERN BUILDERS. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. San Luis, Pagsanghan, Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0019554

₱3,782,550.00 · FY2024

Released to Adiong Memorial State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

431 projects · ₱38.3B total · 3 flags

4. Implementation

Contract Amount

₱97,997,342.94

Progress

Past target date (DPWH On-Going)

Start Date

February 17, 2025

Target End

September 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.