Buildings and Facilities15GA0185

CONST. OF BRGY. ALAMINOS MULTI-PURPOSE BUILDING, ALAMINOS, MADALAG, AKLAN

CONST. OF BRGY. ALAMINOS MULTI-PURPOSE BUILDING, ALAMINOS, MADALAG, AKLAN is a DPWH-tracked public work in Aklan DEO, Region VI. Reported contract value: ₱1,901,711.17. Status: Reported complete (DPWH). Contractor on record: FIRST MAKEEN CONST. Figures trace to dpwh.

Aklan DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Follow the peso

2 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    Not yet linked

  2. 2. SARO / NCA release

    SARO SARO-NCR-16-0013736 · ₱13,590,143

    Possible match · score 0.65

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-16-0013736

₱13,590,143.00 · FY2016

Released to P0400001 - Technological University of the Philippines - Manil (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

264 projects · ₱1.2B total · 0 flags

4. Implementation

Contract Amount

₱1,901,711.17

Progress

Reported complete (DPWH)

Start Date

January 28, 2016

Target End

April 26, 2016

5. Audit