Roads18L00130

ISLAND GARDEN CITY OF SAMAL (IGACOS) CIRCUMFERENTIAL ROAD, (WEST SIDE) PACKAGE 2, DAVAO DEL NORTE

ISLAND GARDEN CITY OF SAMAL (IGACOS) CIRCUMFERENTIAL ROAD, (WEST SIDE) PACKAGE 2, DAVAO DEL NORTE is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱434,250,000.00. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱434,250,000.00

Progress

Reported complete (DPWH)

Start Date

August 6, 2018

Target End

January 2, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.