Roads22CG0236

CONCRETING OF GATIAWIN - LACMIT FMR, BARANGAY GATIAWIN/ LACMIT, ARAYAT, PAMPANGA

CONCRETING OF GATIAWIN - LACMIT FMR, BARANGAY GATIAWIN/ LACMIT, ARAYAT, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱11,342,968.50. Status: Reported complete (DPWH). Contractor on record: CMDV CONST. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure/Slope Protection of Mesalipit Creek, Bacolor, Pampanga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-22-0008313

₱1,519,555.00 · FY2022

Released to Division of Davao Occidental (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

14 projects · ₱143.5M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM; SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATIGIC PUBLIC BUILDINGS/FACILITIES; CONSTRUCTION OF ROADS BRGY PANDAN-TABUN, ANGELES CI

Pampanga 3rd DEO, Region III

2023₱29.4M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); CONSTRUCTION/IMPROVEMENT/REHABILITATION OF MULTIPURPOSE BUILDING IN MABALACAT CITY

Pampanga 3rd DEO, Region III

2023₱27.4M
Reported complete (DPWH)
No sat.

Improvement/Rehabilitation/Construction of Drainage Magalang, Pampanga

MAGALANG (PAMPANGA), PAMPANGA, Region III

2023₱19.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM; CONST/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES, AND ECONOMIC ZONES; (ROADS LEVERGING LINKAGES FOR INDUSTRY AND TRADE INFRA PROGRAM-ROLL-IT) ANGELES CITY TOLL EXIT CONNECTING NLEX AND SCTEX SUPPORT

Pampanga 3rd DEO, Region III

2022₱9.8M
Reported complete (DPWH)
No sat.

Improvement/Rehabilitation/Construction of Drainage Mabalacat City, Pampanga

MABALACAT CITY (PAMPANGA), PAMPANGA, Region III

2023₱9.7M
Reported complete (DPWH)
No sat.

BASIC INFRA PROGRAM, ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES, CONST OF ROAD, BRGY DAU, MABALACAT CITY, PAMPANGA STA. 0+000 TO STA 0+140, STA 0+000 TO STA 0+125, STA 0+000 TO STA 0+185

Pampanga 3rd DEO, Region III

2022₱4.9M
Reported complete (DPWH)
View all 14 projects →

4. Implementation

Contract Amount

₱11,342,968.50

Progress

Reported complete (DPWH)

Start Date

June 28, 2022

Target End

September 25, 2022

5. Audit