Buildings and Facilities24OE0177

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY 601, ZONE 59, STA. MESA, MANILA

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY 601, ZONE 59, STA. MESA, MANILA is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱59,399,903.58. Status: Reported complete (DPWH). Contractor on record: ELITE GEN CONTRACTOR AND DEVELOPMENT CORP. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱12,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-F-24-0016515 · ₱97,500 · release to the district office, not itemized per project

    Possible match · score 0.64

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱58,139,683 · ELITE GEN CONTRACTOR AND DEVELOPMENT CORP

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-03-06 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY 601, ZONE 59, STA. MESA, MANILA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Binondo, Barangay 281, Manila City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-F-24-0016515

₱97,500.00 · FY2024

Released to Regional Office - XIII (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Projects

₱58,139,683.22 · ELITE GEN CONTRACTOR AND DEVELOPMENT CORP

Award / contract ref: 24OE0177

Contractor

121 projects · ₱7.5B total · 3 flags

Other projects by this contractor

Construction of Road Dike along Bucayao River (East Side), Sitio Malinao Section, Barangay Tagumpay, Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱247.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. SAN PEDRO (DOWNSTREAM), SAN JOSE, OC

Region IV-B, Region IV-B

2024₱232.4M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, VILLAFLOR SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱213.9M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, CANLASID SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱193.0M
Past target date (DPWH On-Going)

Construction of Road Dike along Mag-asawang Tubig River, Sitio Dike, Barangay Apitong Section, Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY HINOLASO, DOLORES, EASTERN SAMAR

Region VIII, Region VIII

2024₱190.9M
Past target date (DPWH On-Going)
View all 121 projects →

4. Implementation

Contract Amount

₱59,399,903.58

Progress

Reported complete (DPWH)

Start Date

February 12, 2024

Target End

May 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.