Construction of Revetment24OF0026

Construction of Flood Control Structure at Talayan Creek, Barangay Sto. Domingo, Quezon City

Construction of Flood Control Structure at Talayan Creek, Barangay Sto. Domingo, Quezon City is a DPWH-tracked public work in QUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital Region. Reported contract value: ₱48,508,612.63. Status: Reported complete (DPWH). Contractor on record: AMETHYST HORIZON BUILDERS AND GEN CONTRACTOR AND DEVELOPMENT CORP. Figures trace to sumbong.

QUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Talayan Creek, Barangay Sto. Domingo, Quezon City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000559

₱1,853,574.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008750

₱1,815,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0003156

₱1,401,164.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000560

₱173,180.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008765

₱168,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0003157

₱123,131.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

NCA NCA-ROV-24-0004447

₱9,492,576.00 · FY2024

Released to Quezon City 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

154 projects · ₱9.6B total · 12 flags

4. Implementation

Contract Amount

₱48,508,612.63

Progress

Reported complete (DPWH)

Start Date

February 6, 2024

Target End

December 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.