Flood Control and Drainage24OE0168

CONSTRUCTION OF RETARDING BASIN AT ESTERO DELA REINA (PHASE 13), TONDO, MANILA CITY

CONSTRUCTION OF RETARDING BASIN AT ESTERO DELA REINA (PHASE 13), TONDO, MANILA CITY is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱125,449,036.42. Status: Past target date (DPWH On-Going). Contractor on record: JJPR CONST SERVICES. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Binondo, Barangay 281, Manila City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-F-24-0016515

₱97,500.00 · FY2024

Released to Regional Office - XIII (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

44 projects · ₱4.4B total · 11 flags

4. Implementation

Contract Amount

₱125,449,036.42

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2024

Target End

April 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.