Flood Control and Drainage24OE0168

CONSTRUCTION OF RETARDING BASIN AT ESTERO DELA REINA (PHASE 13), TONDO, MANILA CITY

CONSTRUCTION OF RETARDING BASIN AT ESTERO DELA REINA (PHASE 13), TONDO, MANILA CITY is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱125,449,036.42. Status: Past target date (DPWH On-Going). Contractor on record: JJPR CONST SERVICES. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Follow the peso

4 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱12,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-F-24-0016515 · ₱97,500

    Possible match · score 0.64

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱122,683,119 · JJPR CONSTRUCTION SERVICES

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    97% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · NCR, City of Manila, First District

Based on the coordinates published with the DPWH record and NOAH file Metro Manila.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF RETARDING BASIN AT ESTERO DELA REINA (PHASE 13), TONDO, MANILA CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Binondo, Barangay 281, Manila City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-F-24-0016515

₱97,500.00 · FY2024

Released to Regional Office - XIII (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Projects

₱122,683,119.47 · JJPR CONSTRUCTION SERVICES

Award / contract ref: 24OE0168

Contractor

D

44 projects · ₱4.4B total · 11 flags

4. Implementation

Contract Amount

₱125,449,036.42

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2024

Target End

April 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.