Bridges23F00082

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-NAGA-JCT. MAGARAO-CANAMAN-LIBMANAN JCT. PPH ROAD (SKYBRIDGE), CAMARINES SUR, LIBMANAN, CAMARINES SUR 2ND LEGISLATIVE DISTRICT

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-NAGA-JCT. MAGARAO-CANAMAN-LIBMANAN JCT. PPH ROAD (SKYBRIDGE), CAMARINES SUR, LIBMANAN, CAMARINES SUR 2ND LEGISLATIVE DISTRICT is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱101,324,835.97. Status: Reported complete (DPWH). Contractor on record: G C I CONST AND DEV'T CORP. Figures trace to dpwh.

Region V, Region V
Region: Region V

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23F00082 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2022-01-16 → 2022-01-16

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-NAGA-JCT. MAGARAO-CANAMAN-LIBMANAN JCT. PPH ROAD (SKYBRIDGE), CAMARINES SUR, LIBMANAN, CAMARINES SUR 2ND LEGISLATIVE DISTRICT

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

305 projects · ₱29.5B total · 6 flags

Other projects by this contractor

No sat.

OO1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CAMARINES SUR EXPRESSWAY PROJECT (SAN FERNANDO-PILI), PACKAGE 1, CAMARINES SUR, MINALABAC, CAMARINES SUR 2ND LEGISLATIVE DISTRICT

Region V, Region V

2018₱289.5M
Reported complete (DPWH)
No sat.

OO1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CAMARINES SUR EXPRESSWAY PROJECT (SAN FERNANDO-PILI), PACKAGE 2, CAMARINES SUR, MINALABAC, CAMARINES SUR 2ND LEGISLATIVE DISTRICT

Region V, Region V

2018₱289.5M
Reported complete (DPWH)
No sat.

CLUSTER I-ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-I-I-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY POBLACIO

Region V, Region V

2024₱283.1M
Past target date (DPWH On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES-CONSTRUCTION OF BATO LAKESHORE DIKE ROAD (CIRCUMFERENTIAL ROAD)IN SUPPORT OF AGRIC

Region V, Region V

2023₱279.8M
Reported complete (DPWH)
No sat.

CLUSTER VIII-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-VIII-I: DAANG MAHARLIKA (LZ)-K0399+034-K0399+045, K0400+615-KO401+970; VIII-II: DAANG MAHARLIKA (LZ)-K0414+385-K04

Region V, Region V

2024₱273.7M
Past target date (DPWH On-Going)
No sat.

CLUSTER XI-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-XI-I: CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-CATANDUANES CIR RD-K0003+060-K0003+648, K0003+658-K0

Region V, Region V

2024₱262.5M
Past target date (DPWH On-Going)
View all 305 projects →

4. Implementation

Contract Amount

₱101,324,835.97

Progress

Reported complete (DPWH)

Start Date

August 16, 2023

Target End

September 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.