GAA 2025 OO-125BF0102

OO1: NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MALLIG BYPASS ROAD, PACKAGE 1, ISABELA, MALLIG, ISABELA

OO1: NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MALLIG BYPASS ROAD, PACKAGE 1, ISABELA, MALLIG, ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱38,023,913.53. Status: Past target date (DPWH On-Going). Contractor on record: RRC CO INC FORMERLY: R R C CONST. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Purok Eden and Purok Saranay, Barangay Sinamar, Roxas, Isabela
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-25-0017562

₱-1,460,337.00 · FY2025

Released to Rizal Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

86 projects · ₱3.2B total · 0 flags

4. Implementation

Contract Amount

₱38,023,913.53

Progress

Past target date (DPWH On-Going)

Start Date

October 13, 2025

Target End

May 24, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.