Buildings and Facilities17HE0046

COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY LAGTANG, TALISAY CITY, CEBU

COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY LAGTANG, TALISAY CITY, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱480,140.00. Status: Reported complete (DPWH). Contractor on record: JANUARY BUILDERS. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Binabag Bridge (Upstream & Downstream), Bogo City, Cebu
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-17-0001003

₱1,575,000.00 · FY2017

Released to Luna National High To School ent (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱480,140.00

Progress

Reported complete (DPWH)

Start Date

May 19, 2017

Target End

June 17, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.