Buildings and Facilities16DO0040

CONSTRUCTION OF CLASSROOM IN PILILLA NHS - FOUR (4) STOREY SIXTEEN (16) CLASSROOM AT PILILLA, RIZAL

CONSTRUCTION OF CLASSROOM IN PILILLA NHS - FOUR (4) STOREY SIXTEEN (16) CLASSROOM AT PILILLA, RIZAL is a DPWH-tracked public work in Rizal 2nd DEO, Region IV-A. Reported contract value: ₱28,873,634.70. Status: Reported complete (DPWH). Contractor on record: HONEYVILLECONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Rizal 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱8,512,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation of Flood Mitigation Facilities of Principal River along Upper Marikina River, Rodriguez River, Brgy. San Rafael, Rodriguez (Montalban), Rizal
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0038823

₱276,280.00 · FY2016

Released to Adiong Memo (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

126 projects · ₱6.0B total · 0 flags

4. Implementation

Contract Amount

₱28,873,634.70

Progress

Reported complete (DPWH)

Start Date

December 5, 2016

Target End

March 20, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.