Roads21PA0169

NETWORK DEVELOPMENT PROGRAM PAVING OF UNPAVED ROADS-SECONDARY ROADS, ABRA-KALINGA ROAD, K0472+101.7-K0472+184.4, K0472+184.4-K0472+237.6 (LS), K0472+237.60-K0472-305.30, K0472+357.30-K0472+792.8, K0472+851-K0472+892, K0472+892-K0472+938.5 (LS), K0473+000-

NETWORK DEVELOPMENT PROGRAM PAVING OF UNPAVED ROADS-SECONDARY ROADS, ABRA-KALINGA ROAD, K0472+101.7-K0472+184.4, K0472+184.4-K0472+237.6 (LS), K0472+237.60-K0472-305.30, K0472+357.30-K0472+792.8, K0472+851-K0472+892, K0472+892-K0472+938.5 (LS), K0473+000- is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱72,371,472.73. Status: Reported complete (DPWH). Contractor on record: 739 BUILDERS. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2021 · ₱30,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROXIII-21-0013634 · ₱1,143,000 · release to the district office, not itemized per project

    Possible match · score 0.64

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 21PA0169 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-11-28 → 2023-01-11

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: NETWORK DEVELOPMENT PROGRAM PAVING OF UNPAVED ROADS-SECONDARY ROADS, ABRA-KALINGA ROAD, K0472+101.7-K0472+184.4, K0472+184.4-K0472+237.6 (LS), K0472+237.60-K0472-305.30, K0472+357.30-K0472+792.8, K0472+851-K0472+892, K0472+892-K0472+938.5 (LS), K0473+000-

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Patoc Flood Control, Sta. 0+100 - 0+600, Bucay, Abra
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXIII-21-0013634

₱1,143,000.00 · FY2021

Released to Buenavista National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

623 projects · ₱14.3B total · 27 flags

4. Implementation

Contract Amount

₱72,371,472.73

Progress

Reported complete (DPWH)

Start Date

January 17, 2022

Target End

June 21, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.