Buildings and Facilities18DD0596

CONSTRUCTION OF 4STY20CL, FERNANDO AIRBASE ES, LIPA CITY, BATANGAS

CONSTRUCTION OF 4STY20CL, FERNANDO AIRBASE ES, LIPA CITY, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱46,094,858.54. Status: Reported complete (DPWH). Contractor on record: LIBRIUS CONST. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱10,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-B-18-0016454 · ₱15,000,000 · release to the district office, not itemized per project

    Possible match · score 0.78

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18DD0596 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-04-18 → 2025-08-03

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF 4STY20CL, FERNANDO AIRBASE ES, LIPA CITY, BATANGAS

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection/Revetment at Dayapan Br., Ibaan, Batangas
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-18-0016454

₱15,000,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱46,094,858.54

Progress

Reported complete (DPWH)

Start Date

August 13, 2018

Target End

March 25, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.